Portman Delivers 1st Phase of $330M Philly-Area Project; industrial building spans more than 600K-SF

Portman Holdings has wrapped up the construction of a 636,121-square-foot, Class A logistics facility in Exton, Pa., marking the debut of I-76 Trade Center’s first phase. The $330 million industrial project is set to comprise 1.9 million square feet upon completion.

Work kicked off in 2023 after Portman purchased the land. KSS Architects designed the development with Alston serving as the general contractor. Bank OZK issued a $60 million construction note one year later, CommercialEdge shows.